BVUSD Education Foundation Maple Hills Sports Complex
Project Summary
Bear Valley Unified School District Education (2021)
The project consists of a three field multi-use baseball / softball / soccer complex occupying approximately 15 acres. Access to the
complex from 44450 Baldwin Lane will be via a newly constructed 800 foot access road. 110 parking spaces are planned on the
westerly and southwesterly side of the complex. Improvements include four backstops and an approximately 750 sq. ft. prefabricated
restroom / concession stand. Site grading will require placement of approximately 154,000 cubic yards of compacted fill soil, with cuts
as deep as 300 feet and canyon fills as deep as 55 feet.
IFE Role
IFE was retained by the Bear Valley USD
Education Foundation to complete a
geotechnical investigation and geologic hazards
study for the project. Our services included the
following:
- Site geology review and geologic mapping
- Regional and local earthquake fault and seismicity evaluation
- 10 exploratory borings to depths of 50 feet
- Laboratory testing for geotechnical design parameters
- Seismic refraction survey for excavation and rippability analysis
- Infiltration testing
- Stability analysis of proposed cut and fill slopes
- Development of recommendations for design and construction
- Preparation of a comprehensive engineering geology and geotechnical investigation report